Skip to content
Our portfolio / Blåsmark

Blåsmark

Northern Sweden

Power source
Onshore Wind
Capacity
60–100 MW
Stage
Development

About Blåsmark

Fu-Gen acquired the Blåsmark project rights from Alpiq in 2019 and is now looking to develop a project of 63 MW.

The project is located in Piteå municipality and the site already has optimal and proven wind resources due to a four year measurement campaign.

Timeline

2022
Ongoing dialogue with municipality and landowners
2020
Completed renewal of land leases of the Blåsmark project
2019
Fu-Gen acquired project rights from Alpiq and started repermitting process for a smaller number of turbines (15) with a total height of 230m
2012
Permit entered into force for 25 turbines with a total height of 150m

Facts

Blåsmark

Northern Sweden

Power source
Onshore Wind
Capacity
60–100 MW
Stage
Development
Country
Sweden
Region
Norrbotten

Contact information

Jennie Hallgren
Project Development Director